NPRR #1304 · Revision Request
NPRR1304 Move OBD to Section 22 – Procedure for Identifying Resource Nodes
ReasonGeneral system and/or process improvement(s)
Created2025-11-12
Approved2026-03-26
Sections Affected
23.8.23.10.3.1and 22R (new)
Summary
This Nodal Protocol Revision Request (NPRR) incorporates the Other Binding Document “Procedure for Identifying Resource Nodes” into the Protocols to standardize the approval process.
Timeline
- Oct 28 '25
-
Nov 12 '25
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“to recommend approval of NPRR1304 as submitted” — Passed→ Impact Analysis Cpnsideration
-
Dec 10 '25
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 11/12/25 PRS Report and 10/28/25 Impact Analysis for NPRR1304” — Passed→ Revision Request Consideration
-
Jan 21 '26
TAC TAC MeetingTACRecommended for Approval Recommended for approval“to recommend approval of NPRR1304 as recommended by PRS in the 12/10/25 PRS Report” — Passed→ Revision Request Consideration
- Feb 9 '26
-
Feb 10 '26
BOARDEmail Vote / Unlisted MeetingBOARDRecommended for Approval Recommended for approval“to recommend approval of NPRR1304 as recommended by TAC in the 1/21/26 TAC Report” — Passed→ Revision Request Consideration
-
Mar 26 '26
PUCTPUCTApproved Approved“to approve NPRR1304 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
-
—
Posted since the last meeting