NPRR #1299 · Revision Request
NPRR1299 Clarifications to Emergency Response Service (ERS)
ReasonGeneral system and/or process improvement(s)
Created2025-09-17
Approved2026-01-15
Sections Affected
3.14.3.13.14.3.4and 8.1.3.1.2
Summary
This Nodal Protocol Revision Request (NPRR) addresses four independent issues related to Emergency Response Service (ERS): 1) Paragraph (5)(c) of Section 3.14.3.1 is incorrectly included as a subparagraph of paragraph (5) and instead should be paragraph (6) of Section 3.14.3.1. 2) In paragraph (3)(j) of Section 3.14.3.4 the ERS Preliminary Baseline Review Results document is being removed from the Market Information System (MIS) posting list because it is a legacy report that is no longer needed. The information previously provided by the posting of that document has been replaced by the mandatory ERS Resource Identification (ERID) process to get this information and is no longer applicable or being requested by Qualified Scheduling Entities (QSEs). 3) A timing change to paragraph (6) of Section 3.14.3.4 provides flexibility for the ERS offer posting requirement so that instead of posting exactly on the 60th day after the first day of the ERS Standard Contract Term (SCT) there will now be a window for posting no sooner than 60 days and no later than 65 days after the first day of the ERS SCT. 4) A change to paragraph (2) of Section 8.1.3.1.2 clarifies that for non-weather sensitive ERS Loads to be classified as co-located with an ERS Generator, both must be awarded in the same service type and for all the same ERS Time Periods. This has been an issue when both are offered into the same service type and/or Time Periods but for various reasons not awarded.
Timeline
- Sep 2 '25
-
Sep 17 '25
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Sep 16 '25 ERCOT comments“to recommend approval of NPRR1299 as amended by the 9/16/25 ERCOT comments” — Passed→ Impact Analysis Consideration
-
Oct 8 '25
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 9/17/25 PRS Report and 9/2/25 Impact Analysis for NPRR1299” — Passed→ Revision Request Consideration
-
Oct 22 '25
TAC TAC MeetingTACRecommended for Approval Recommended for approval“to recommend approval of NPRR1299 as recommended by PRS in the 10/8/25 PRS Report” — Passed→ Revision Request Consideration
-
Dec 8 '25
BOARD Board of Directors MeetingBOARDRecommended for Approval Recommended for approval“to recommend approval of NPRR1299 as recommended by TAC in the 10/22/25 TAC Report” — Passed→ Revision Request Consideration
-
Jan 15 '26
PUCTPUCTApproved Approved“to approve NPRR1299 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
-
—
Posted since the last meeting