NPRR #1290 · Revision Request
NPRR1290 Gap Resolutions and Clarifications for the Implementation of RTC+B
ReasonGeneral system and/or process improvement(s)
Created2025-07-16
Approved2025-11-06
Sections Affected
2.12.23.1.6.93.17.23.184.4.7.14.4.9.3.14.4.9.5.14.4.9.6.14.4.9.7.14.4.9.84.4.9.8.16.36.5.5.26.5.7.36.5.7.3.16.5.7.56.6.3.16.6.96.6.9.16.7.5.56.7.5.67.9.1.38.1.1.2.1.216.11.4.1and 22P
Summary
This Nodal Protocol Revision Request (NPPR) addresses several gaps and provides necessary clarifications in the Protocol language to support implementation of the Real-Time Co-optimization plus Batteries (RTC+B) initiative.
Timeline
- May 28 '25
- Jun 18 '25
-
Jun 20 '25
Listed without action at 1 meeting
- Jul 9 '25
-
Jul 16 '25
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Jul 2 '25 HEN comments“To recommend approval of NPRR1290 as amended by the 7/2/25 HEN comments” — Passed→ PRS for Impact Analysis consideration
- Jul 23 '25
-
Aug 7 '25
Listed without action at 1 meeting
-
Aug 13 '25
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC priority 2026 · rank 4800“To endorse and forward to TAC the 7/16/25 PRS Report as revised by PRS and 8/12/25 Revised Impact Analysis for NPRR1290 with a recommended priority of 2026 and rank of 4800 for Phase 2” — Passed→ TAC for consideration
- Aug 19 '25
-
Aug 27 '25
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR1290 as recommended by PRS in the 8/13/25 PRS Report” — Passed→ Board for consideration
-
Sep 22 '25
BOARD Board of Directors MeetingBOARDRecommended for Approval Recommended for approval“To recommend approval of NPRR1290 as recommended by TAC in the 8/27/25 TAC Report” — Passed→ PUCT for consideration
-
Nov 6 '25
PUCTPUCTApproved Approved“To approve NPRR1290 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
- Feb 18 '26
-
Mar 11 '26
Listed without action at 3 meetings (Mar 11 '26 – Apr 20 '26)