ERCOT·WATCH Search ercot.com  ⌕
NPRR #1283 · Revision Request

NPRR1283  Modification of SSR Mitigation Timeline

Approved sponsor ERCOT posted 2025-04-29 ercot.com
ReasonGeneral system and/or process improvement(s)
Created2025-05-14
Approved2025-11-06
Sections Affected
3.22.1.23.22.1.33.22.1.4and 16.5
Summary
This Nodal Protocol Revision Request (NPRR) changes the current requirement that any required SSR studies be complete and mitigation be in place prior to Initial Synchronization of a new Generation Resource, Energy Storage Resource (ESR), or Settlement Only Generator (SOG). Based on recognition that SSFR can be a risk upon energization, this NPRR requires that these steps now be completed prior to Initial Energization to ensure that SSFR risk has been evaluated and mitigated.
Timeline