NPRR1272 Voltage Support at Private Use Networks
ReasonGeneral system and/or process improvement(s)
Created2025-03-12
Sections Affected
3.15
Summary
This Nodal Protocol Revision Request (NPRR) clarifies that Section 3.15 should be applied to require ERCOT to independently evaluate the Reactive Power requirements of Generation Resources excluding the effects of co-located retail load. As such, any Generation Resources that meet the requirements of the Protocols as standalone Generation Resources shall not have additional Reactive Power requirements imposed as a result of co-locating with load. Further, the language clarifies that the onsite load must also comply with the power factor requirements for retail Customers in the applicable tariff for retail delivery service.
Timeline
-
Feb 5 '25
PRSFiled by Occidental Chemical Corporation
-
Feb 12 '25
Listed without action at 2 meetings (Feb 12 '25 – Mar 6 '25)
-
Mar 12 '25
PRS PRS MeetingPRSDeferred/Tabled Tabled Referred → ROS“to table NPRR1272 and refer the issue to ROS” — Passed→ Language Consideration
-
Apr 3 '25
ROS ROS Meeting - Webex Only“To request PRS continue to table NPRR1272 for further review by PLWG and VPWG”
- Apr 9 '25
- May 1 '25
-
May 6 '25
Listed without action at 2 meetings (May 6 '25 – May 14 '25)
- Jun 5 '25
-
Jun 11 '25
Listed without action at 28 meetings (Jun 11 '25 – Aug 6 '26)
- PRS Meeting
- ROS Meeting - Webex Only
- PRS Meeting
- ROS Meeting
- PRS Meeting
- ROS Meeting - Webex Only
- PRS Meeting
- ROS Meeting
- PRS Meeting
- ROS Meeting - Webex Only
- PRS Meeting
- ROS Meeting - Webex Only
- PRS Meeting
- ROS Meeting
- PRS Meeting
- ROS Meeting
- PRS Meeting
- ROS Meeting
- PRS Meeting
- ROS Meeting
- PRS Meeting
- PRS Meeting
- ROS Meeting
- ROS Meeting
- PRS Meeting
- ROS Meeting - Webex Only
- PRS Meeting
- ROS Meeting