NPRR #1270 · Revision Request
NPRR1270 Additional Revisions Required for Implementation of RTC
ReasonGeneral system and/or process improvement(s)
Created2025-02-12
Approved2025-05-15
Sections Affected
6.5.5.26.5.7.6.2.36.5.9.4.28.1.1.2.1.38.1.1.2.1.7and 8.1.1.4.3
Summary
This Nodal Protocol Revision Request (NPRR): Updates requirements for Load Resources that are changing under Real-Time Co-optimization (RTC) and were not updated in earlier revisions; removes language associated with Group assignments in the Day-Ahead Market (DAM); deployments are Resource-specific based on Real-Time awards; no requirement to return to service in three hours as that capacity will be replaced with awarded capacity in Real-Time; eliminates the automatic qualification of all Resources to provide On-Line Non-Spinning Reserve (Non-Spin) and Security-Constrained Economic Dispatch (SCED)-dispatchable ERCOT Contingency Reserve Service (ECRS). Resources will be required to undergo a qualification test to provide each of these services; and adds additional pre-processing checks in the SCED process to validate Ancillary Service capability telemetry that are sent by Qualified Scheduling Entities (QSEs).
Timeline
- Jan 28 '25
- Feb 12 '25
-
Mar 12 '25
PRS PRS MeetingPRSRecommended for Approval Urgent status Recommended for approval Forwarded → TAC“To grant NPRR1270 Urgent status; to recommend approval of NPRR1270 as submitted; and to forward to TAC NPRR1270 and the 1/28/25 Impact Analysis” — Passed→ TAC for consideration
-
Mar 26 '25
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR1270 as recommended by PRS in the 3/12/25 PRS Report” — Passed→ Board for consideration
- Apr 7 '25
-
Apr 8 '25
BOARDEmail Vote / Unlisted MeetingBOARDRecommended for Approval Recommended for approval“To recommend approval of NPRR1270 as recommended by TAC in the 3/26/25 TAC Report” — Passed→ PUCT for consideration
-
May 15 '25
PUCTPUCTApproved Approved“To approve NPRR1270 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
-
—
Posted since the last meeting