NPRR #1258 · Revision Request
NPRR1258 TSP Performance Monitoring Update
ReasonGeneral system and/or process improvement(s)
Created2024-11-14
Approved2025-03-13
Sections Affected
8.3
Summary
This Nodal Protocol Revision Request (NPRR) removes language from Section 8.3 that is duplicative of requirements that are detailed in Section 3, Management Activities for the ERCOT System. The provisions at issue provide model update requirements that are designed to ensure network data is in Common Information Model (CIM) format and uses the required naming convention.
Timeline
- Oct 29 '24
-
Nov 14 '24
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“to recommend approval of NPRR1258 as submitted” — Passed→ Impact Analysis Consideration
-
Dec 12 '24
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 11/14/24 PRS Report and 10/29/24 Impact Analysis for NPRR1258” — Passed→ Revision Request Consideration
-
Jan 22 '25
TAC TAC Meeting - Webex OnlyTACRecommended for Approval Recommended for approval“to recommend approval of NPRR1258 as recommended by PRS in the 12/12/24 PRS Report” — Passed→ Revision Request Consideration
-
Feb 4 '25
BOARD Board of Directors MeetingBOARDRecommended for Approval Recommended for approval“to recommend approval of NPRR1258 as recommended by TAC in the 1/22/25 TAC Report” — Passed→ Revision Request Consideration
-
Mar 13 '25
PUCTPUCTApproved Approved“to approve NPRR1258 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
-
—
Posted since the last meeting