NPRR #1253 · Revision Request
NPRR1253 Incorporate ESR Charging Load Information into ICCP
ReasonStrategic Plan Objective 2
Created2024-10-17
Approved2025-03-13
Sections Affected
6.3.2
Summary
This Nodal Protocol Revision Request (NPRR) 1253 includes Wholesale Storage Load (WSL) charging load to the dataset ERCOT provides via Inter-Control Center Communications Protocol (ICCP).
Timeline
- Oct 1 '24
- Oct 17 '24
-
Nov 14 '24
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Oct 10 '24 ERCOT comments“to recommend approval of NPRR1253 as amended by the 10/10/24 ERCOT comments” — Passed→ Impact Analysis Consideration
- Nov 18 '24
-
Dec 12 '24
PRS PRS MeetingPRSDeferred/Tabled Tabled“to table NPRR1253” — Passed→ Impact Analysis Consideration
- Dec 19 '24
-
Jan 15 '25
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC priority 2025 · rank 4225“to endorse and forward to TAC the 12/12/24 PRS Report and 1/14/25 Impact Analysis for NPRR1253 with a recommended priority of 2025 and rank of 4225” — Passed→ Revision Request Consideration
-
Jan 22 '25
TAC TAC Meeting - Webex OnlyTACRecommended for Approval Recommended for approval“to recommend approval of NPRR1253 as recommended by PRS in the 1/15/25 ROS Report” — Passed→ Revision Request Consideration
- Jan 30 '25
-
Feb 4 '25
BOARD Board of Directors MeetingBOARDRecommended for Approval Recommended for approval“to recommend approval of NPRR1253 as recommended by TAC in the 1/22/25 TAC Report and the 1/24/25 Revised Impact Analysis” — Passed→ Revision Request Consideration
- Feb 27 '25
-
Mar 13 '25
PUCTPUCTApproved Approved“to approve NPRR1253 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
- Apr 24 '25
-
May 29 '25
Listed without action at 2 meetings (May 29 '25 – Jan 22 '26)