NPRR #1234 · Revision Request
NPRR1234 Interconnection Requirements for Large Loads and Modeling Standards for Loads 25 MW or Greater
ReasonStrategic Plan Objective 1
Created2024-06-13
Approved2025-05-15
Sections Affected
2.12.23.1.13.1.5.113.3.23.10.7.23.10.7.53.10.7.5.13.153.15.33.223.22.13.22.1.13.22.1.23.22.1.33.22.1.4 (new)3.22.1.43.22.23.22.316.5and ERCOT Fee Schedule
Summary
This Nodal Protocol Revision Request (NPRR) and the related PGRR establish interconnection and modeling requirements for “Large Loads”—defined in this NPRR to refer to one or more Facilities at a single site with an aggregate peak power Demand of 75 MW or more. ERCOT proposes these requirements based upon its experience with the interim large Load interconnection process implemented on March 25, 2022, analysis of operational events, and the discussion of various issues concerning Large Loads explored by the Large Flexible Load Task Force (LFLTF). Additionally, this NPRR facilitates the addition of a new study process for Large Loads seeking to interconnect to the ERCOT system. This process is described in the accompanying PGRR. This NPRR also adds a requirement that any Resource Entity that adds 20 MW or more of Load at any site with an existing Generation Resource shall submit a new Reactive Power study. The study must demonstrate the continued compliance of the Generation Resource with Voltage Support Service (VSS) requirements. This NPRR also establishes specific Subsynchronous Oscillation (SSO) requirements for Large Loads and revises and supplements SSO-related definitions, in addition to clarifying existing SSO requirements. Furthermore, although the primary focus of this NPRR is Loads that are 75 MW or larger, this NPRR also establishes new standards for the identification and classification of a site with an aggregate peak Demand of 25 MW or more at a common substation in ERCOT Network Operations Model. Such information will provide ERCOT visibility of the locations of these Loads for operational and planning purposes. Finally, this NPRR adds a fee for Large Load Interconnection Study Requests to the ERCOT Fee Schedule.
Timeline
- May 28 '24
-
Jun 3 '24
Listed without action at 3 meetings (Jun 3 '24 – Jun 12 '24)
-
Jun 13 '24
PRS PRS MeetingPRSDeferred/Tabled Tabled Referred → ROS“To table NPRR1234 and refer the issue to ROS” — Passed→ PRS for consideration
-
Jul 11 '24
ROS ROS Meeting - Webex Only“To request PRS continue to table NPRR1234 for further review by NDSWG”
-
Jul 16 '24
Listed without action at 4 meetings (Jul 16 '24 – Aug 8 '24)
- Aug 13 '24
- Aug 20 '24
-
Sep 9 '24
Listed without action at 2 meetings (Sep 9 '24 – Sep 12 '24)
- Sep 24 '24
-
Oct 3 '24
Listed without action at 4 meetings (Oct 3 '24 – Nov 7 '24)
- Nov 12 '24
-
Nov 14 '24
Listed without action at 2 meetings (Nov 14 '24 – Dec 5 '24)
- Dec 12 '24
- Dec 17 '24
-
Dec 18 '24
Listed without action at 4 meetings (Dec 18 '24 – Jan 21 '25)
- Jan 29 '25
- Feb 6 '25
-
Feb 12 '25
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Jan 24 '25 ERCOT comments“To recommend approval of NPRR1234 as amended by the 1/24/25 ERCOT comments” — Passed→ PRS for Impact Analysis consideration
- Mar 6 '25
-
Mar 12 '25
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC priority 2026 · rank 4730“To endorse and forward to TAC the 2/12/25 PRS Report and 5/28/24 Impact Analysis for NPRR1234 with a recommended priority of 2026 and rank of 4730” — Passed→ TAC for consideration
-
Mar 26 '25
TAC TAC MeetingTACRecommended for Approval Recommended for approval Amended by the Mar 25 '25 ERCOT comments“To recommend approval of NPRR1234 as recommended by PRS in the 3/12/25 PRS Report as amended by the 3/25/25 ERCOT comments as revised by TAC” — Passed→ Board for consideration
- Apr 7 '25
-
Apr 8 '25
BOARDEmail Vote / Unlisted MeetingBOARDRecommended for Approval Recommended for approval“To recommend approval of NPRR1234 as recommended by TAC in the 3/26/25 TAC Report” — Passed→ PUCT for consideration
-
May 15 '25
PUCTPUCTApproved Approved“To approve NPRR1234 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
-
Jul 15 '25
Listed without action at 2 meetings (Jul 15 '25 – Dec 18 '25)