NPRR #1229 · Revision Request
NPRR1229 Real-Time Constraint Management Plan Cost Recovery Payment
ReasonGeneral system and/or process improvement(s)
Created2024-06-13
Approved2025-07-31
Sections Affected
4.4.9.3.36.6.3.9 (new)6.6.3.10 (new)6.6.3.11 (new)and 9.5.3
Summary
This Nodal Protocol Revision Request (NPRR) creates a process that compensates a Qualified Scheduling Entity (QSE) when a Constraint Management Plan (CMP) or ERCOT-directed switching instruction implemented by ERCOT causes the trip of a Generation Resource when it would not have occurred absent those conditions.
Timeline
- May 6 '24
- May 9 '24
-
Jun 13 '24
PRS PRS MeetingPRSDeferred/Tabled Tabled Referred → ROS Referred → WMS“To table NPRR1229 and refer the issue to ROS and WMS” — Passed→ PRS for consideration
- Jul 10 '24
- Jul 11 '24
-
Jul 18 '24
Listed without action at 9 meetings (Jul 18 '24 – Sep 12 '24)
- Sep 24 '24
-
Oct 3 '24
Listed without action at 2 meetings (Oct 3 '24 – Oct 7 '24)
- Oct 17 '24
-
Oct 18 '24
Listed without action at 1 meeting
- Nov 6 '24
-
Nov 7 '24
Listed without action at 7 meetings (Nov 7 '24 – Dec 12 '24)
- Jan 6 '25
-
Jan 8 '25
Listed without action at 3 meetings (Jan 8 '25 – Jan 15 '25)
- Jan 30 '25
-
Feb 5 '25
Listed without action at 1 meeting
-
Feb 6 '25
ROS ROS Meeting - Webex Only“To advise PRS that ROS has concluded discussion of NPRR1229 and has determined the issues are financial in nature and has no recommendation at this time”
-
Feb 12 '25
Listed without action at 1 meeting
-
Mar 5 '25
WMS WMS Meeting - Webex Only“To endorse NPRR1229 as amended by the 2/26/25 STEC comments as revised by WMS”
-
Mar 12 '25
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Mar 6 '25 WMS comments“To recommend approval of NPRR1229 as amended by the 3/6/25 WMS comments as revised by PRS” — Passed→ PRS for Impact Analysis consideration
-
Apr 9 '25
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC Amended by the Mar 20 '25 ERCOT comments priority 2028 · rank 5100“To endorse and forward to TAC the 3/12/25 PRS Report as amended by the 3/20/25 ERCOT comments and the 4/8/25 Impact Analysis for NPRR1229 with a recommended effective date of upon system implementation for Section 9.5.3 with a recommended priority of 2028 and rank of 5100 and the first of the month following PUCT approval for the remaining sections” — Passed→ TAC for consideration
-
Apr 23 '25
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR1229 as recommended by PRS in the 4/9/25 PRS Report” — Passed→ Board for consideration
- Jun 23 '25
-
Jun 24 '25
BOARDEmail Vote / Unlisted MeetingBOARDRecommended for Approval Recommended for approval“To recommend approval of NPRR1229 as recommended by TAC in the 4/23/25 TAC Report” — Passed→ PUCT for consideration
-
Jul 31 '25
PUCTPUCTApproved Approved“To approve NPRR1229 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
-
—
Posted since the last meeting