NPRR #1225 · Revision Request
NPRR1225 Exclusion of Lubbock Load from Securitization Charges
ReasonRegulatory requirements
Created2024-05-09
Approved2024-09-26
Sections Affected
26.227.3and 27.5.4
Summary
This Nodal Protocol Revision Request (NPRR) updates the Protocols to align with the Public Utility Commission of Texas’s (PUCT’s) decisions in PUCT Docket No. 56119, Petition of Electric Reliability Council of Texas, Inc. for Expedited Declaratory Order Regarding Public Utility Regulatory Act Chapter 39, Subchapter N; and Docket No. 56122, Petition of Electric Reliability Council of Texas, Inc. for Expedited Declaratory Order Regarding Public Utility Regulatory Act Chapter 39, Subchapter M. To comply with the PUCT’s declaratory orders, ERCOT changed its Settlement systems to implement the PUCT-ordered exclusions to be effective on or before March 4, 2024, the day on which the transfer of Lubbock Power and Light (LP&L) retail Customers to Retail Electric Providers (REPs) began. This NPRR reflects in the Protocols those exclusions.
Timeline
- Apr 11 '24
-
May 9 '24
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of NPRR1225 as submitted” — Passed→ PRS for Impact Analysis consideration
-
Jun 13 '24
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward to TAC the 5/9/24 PRS Report and 4/11/24 Impact Analysis for NPRR1225” — Passed→ TAC for consideration
-
Jun 24 '24
TAC TAC Meeting - Webex OnlyTACRecommended for Approval Recommended for approval“To recommend approval of NPRR1225 as recommended by PRS in the 6/13/24 PRS Report” — Passed→ Board for consideration
-
Aug 20 '24
BOARD Board of Directors MeetingBOARDRecommended for Approval Recommended for approval“To recommend approval of NPRR1225 as recommended by TAC in the 6/24/24 TAC Report” — Passed→ PUCT for consideration
-
Sep 26 '24
PUCTPUCTApproved Approved“To approve NPRR1225 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
-
—
Posted since the last meeting