NPRR #1214 · Revision Request
NPRR1214 Reliability Deployment Price Adder Fix to Provide Locational Price Signals, Reduce Uplift and Risk
ReasonStrategic Plan Objective 2
Created2024-01-11
Sections Affected
2.13.2.53.5.2.13.5.2.23.5.2.33.5.2.43.5.2.53.5.2.63.5.2.74.4.115.5.25.7.1.35.7.1.46.3.26.5.7.36.5.7.3.16.5.9.26.6.1.16.6.1.26.6.1.66.6.1.7 (delete)6.6.3.16.6.3.66.6.3.86.6.6.36.6.6.106.7.56.7.66.9 (new)6.9.1 (new)6.9.2 (new)and 9.5.3
Summary
This Nodal Protocol Revision Request (NPRR) revises the Real-Time On-Line Reliability Deployment Price Adder (RTRDPA) to: send appropriate locational price signals to avoid counterproductive Load and Resource responses to RTRDPA price signals under Real-Time Co-optimization (RTC); limit Resource payment to the actual “indifference payment” (consistent with its definition), thereby reducing associated uplift by eliminating the future need for RTRDPA payments to Resources that exacerbate constraints and eliminating payments to available capacity not requiring an indifference payment; eliminate any future need for the Ancillary Service Imbalance Payments or Charges (ASIP/C) type of indifference payment associated with RTRDPA, thereby reducing the risk associated with providing Ancillary Services; provide Resources an indifference payment under RTC to eliminate the potentially large incentive to ignore Base Point instructions that would likely cause serious reliability issues; and provide a stronger locational price signal around Resources committed by the Reliability Unit Commitment (RUC) process or other reliability actions for congestion, thereby reducing RUC Make-Whole Payment-related charges and uplifts and appropriately compensating impacted Qualified Scheduling Entities (QSEs).
Timeline
- Dec 7 '23
-
Jan 11 '24
PRS PRS MeetingPRSDeferred/Tabled Tabled Referred → WMS“To table NPRR1214 and refer the issue to WMS” — Passed→ PRS for consideration
- Feb 7 '24
- Feb 8 '24
-
Mar 6 '24
Listed without action at 13 meetings (Mar 6 '24 – Aug 8 '24)
- Sep 11 '24
-
Sep 12 '24
Listed without action at 5 meetings (Sep 12 '24 – Oct 17 '24)
- Nov 6 '24
-
Nov 14 '24
Listed without action at 6 meetings (Nov 14 '24 – Jan 15 '25)
- Feb 5 '25
-
Feb 12 '25
Listed without action at 2 meetings (Feb 12 '25 – Feb 18 '25)
- Mar 5 '25
-
Mar 12 '25
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Jan 28 '25 ERCOT comments“To recommend approval of NPRR1214 as amended by the 1/28/25 ERCOT comments” — Passed→ PRS for Impact Analysis consideration
- Apr 9 '25
- May 14 '25
- Jun 11 '25
-
Jul 16 '25
Listed without action at 11 meetings (Jul 16 '25 – May 6 '26)
-
Jun 10 '26
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Jun 5 '26 ERCOT comments Forwarded → PRS“To endorse the 5/14/25 PRS Report as amended by the 6/5/26 ERCOT comments for NPRR1214; and to bring the Revised Impact Analysis back to PRS” — Passed→ PRS for consideration
- Jul 15 '26