NPRR #1166 · Revision Request
NPRR1166 Protected Information Status of DC Tie Schedule Information
ReasonRegulatory requirements
Created2023-04-13
Approved2023-07-20
Sections Affected
1.3.1.1
Summary
This Nodal Protocol Revision Request (NPRR) changes the expiration date for the Protected Information status of Direct Current Tie (DC Tie) Schedule information from 60 days after the applicable Operating Day to the date on which ERCOT files the report with the Public Utility Commission of Texas (PUCT) that is required by P.U.C. SUBST. R. 25.192, Transmission Rates for Export from ERCOT, relating to energy imported and exported over DC Ties interconnected to the ERCOT System. This brings the ERCOT Protocols into alignment with current PUCT Rules.
Timeline
- Mar 7 '23
-
Apr 13 '23
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“to recommend approval of NPRR1166 as submitted” — Passed→ Impact Analysis Consideration
-
May 10 '23
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 4/13/23 PRS Report and the 3/7/23 Impact Analysis for NPRR1166” — Passed→ Revision Request Consideration
-
May 23 '23
TAC TAC Meeting - Webex OnlyTACRecommended for Approval Recommended for approval“to recommend approval of NPRR1166 as recommended by PRS in the 5/10/23 PRS Report” — Passed→ Revision Request Consideration
-
Jun 20 '23
BOARD Board of Directors MeetingBOARDRecommended for Approval Recommended for approval“to recommend approval of NPRR1166 as recommended by TAC in the 5/23/23 TAC Report” — Passed→ Revision Request Consideration
-
Jul 20 '23
PUCTPUCTApproved Approved“to approve NPRR1166 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Rules Adopted by the Independent Organization” — Passed