NPRR #1136 · Revision Request
NPRR1136 Updates to Language Regarding a QSE Moving Ancillary Service Responsibility Between Resources
ReasonAddresses current operational issues
Created2022-06-09
Approved2022-09-15
Sections Affected
4.4.7.3 and 6.4.7
Summary
This Nodal Protocol Revision Request (NPRR) makes changes to reflect the logic that will be in place after the implementation of Fast Frequency Response (FFR) Advancement project, the next phase of implementation for NPRR863, Creation of ERCOT Contingency Reserve Service and Revisions to Responsive Reserve. Specifically, the NPRR adds new paragraph (5) of Section 4.4.7.3 to align with language in Section 6.4.7. These changes are for clarity only, and do not modify the system design. The new paragraph (6) of Section 4.4.7.3 is an additional check that needs to be in place to ensure a QSE does not replace a Regulation Service with Fast Responding Regulation Service (FRRS). This section does not need to be addressed in the FFR Advancement implementation, and it is ERCOT’s intent to implement this logic change in a future project.
Timeline
- May 18 '22
-
Jun 9 '22
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of NPRR1136 as submitted” — Passed→ PRS for Impact Analysis consideration
-
Jul 13 '22
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC priority 2023 · rank 3720“To endorse and forward to TAC the 6/9/22 PRS Report and 5/18/22 Impact Analysis for NPRR1136 with a recommended priority of 2023 and rank of 3720” — Passed→ TAC for consideration
-
Jul 27 '22
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval“To recommend approval of NPRR1136 as recommended by PRS in the 7/13/22 PRS Report” — Passed→ Board for consideration
-
Aug 16 '22
BOARD Board of Directors MeetingBOARDRecommended for Approval Recommended for approval“To recommend approval of NPRR1136 as recommended by TAC in the 7/27/22 TAC Report” — Passed→ PUCT for consideration
-
Sep 15 '22
PUCTPUCTApproved Approved“To approve NPRR1136 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization” — Passed
-
—
Posted since the last meeting