NPRR #1124 · Revision Request
NPRR1124 Recovering Actual Fuel Costs through RUC Guarantee
ReasonAddresses current operational issues; Market efficiencies or enhancements
Created2022-04-06
Approved2022-05-12
Sections Affected
9.14.7
Summary
This Nodal Protocol Revision Request (NPRR) proposes a change to ensure Generation Resources recover their actual fuel costs when instructed to start due to a RUC. Specifically, this NPRR recommends that the Startup Price per start (SUPR) and the Minimum-Energy Price (MEPR), as defined in paragraph (6) of Section 5.7.1.1, RUC Guarantee, will be set to the Startup Cap (SUCAP) and the Minimum-Energy Cap (MECAP), respectively, utilizing the actual approved fuel price paid.
Timeline
- Mar 9 '22
-
Apr 6 '22
PRS Special PRS MeetingPRSRecommended for Approval Urgent status Recommended for approval Forwarded → TAC“to grant NPRR1124 Urgent status; to recommend approval of NPRR1124 as submitted; and to forward to TAC NPRR1124 and the Impact Analysis” — Passed→ Revision Request Consideration
-
Apr 13 '22
TAC TAC MeetingTACRecommended for Approval Recommended for approval“to recommend approval of NPRR1124 as recommended by PRS in the 4/6/22 PRS Report with a recommended effective date of following PUCT approval – May 13, 2022” — Passed→ Revision Request Consideration
-
Apr 28 '22
BOARD Board of Directors MeetingBOARDRecommended for Approval Recommended for approval“to recommend approval of NPRR1124 as recommended by TAC in the 4/13/22 TAC Report. There was one opposing vote” — Passed→ Revision Request Consideration
-
May 12 '22
PUCTPUCTApproved Approved“to approve NPRR1124 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization” — Passed
-
—