NPRR #112 · Revision Request

NPRR112  Emergency Base Point Price Revision

Approved sponsor ERCOT Staff posted 2008-03-03 ercot.com
ReasonThis NPRR is being proposed in order to: 1) Establish a methodology to extend the Energy Offer Curve to allow determination of Emergency Base Point Price.2) Redefine methodology to calculate the Emergency Base Point Price, as requested by the Transition Plan Task Force (TPTF).
Created2008-03-20
Approved2008-07-15
Sections Affected
6.6.9.1Payment for Emergency Power Increase Directed by ERCOT
Summary
This Nodal Protocol Revision Request (NPRR) clarifies the calculation of the Emergency Base Point Price per QSE per Resource by interval (EBPPR) variable.