NPRR #1118 · Revision Request

NPRR1118  Clarifications to the OSA Process

Approved sponsor ERCOT posted 2022-01-25 ercot.com
ReasonAddresses current operational issues / Market efficiencies or enhancements / Regulatory requirements
Created2022-02-09
Approved2022-11-03
Sections Affected
3.1.6.9 and 5.6.5.2
Summary
This Nodal Protocol Revision Request (NPRR) clarifies the Outage Schedule Adjustment (OSA) process based on lessons learned from performing this process during 2021, as well as other factors. The first set of changes improves the terminology and clarifies the process for issuing Advanced Action Notices (AANs) and OSAs. The second set of changes clarify offer submission and Reliability Unit Commitment (RUC) procedures after an OSA is issued.