NPRR #1118 · Revision Request
NPRR1118 Clarifications to the OSA Process
ReasonAddresses current operational issues / Market efficiencies or enhancements / Regulatory requirements
Created2022-02-09
Approved2022-11-03
Sections Affected
3.1.6.9 and 5.6.5.2
Summary
This Nodal Protocol Revision Request (NPRR) clarifies the Outage Schedule Adjustment (OSA) process based on lessons learned from performing this process during 2021, as well as other factors. The first set of changes improves the terminology and clarifies the process for issuing Advanced Action Notices (AANs) and OSAs. The second set of changes clarify offer submission and Reliability Unit Commitment (RUC) procedures after an OSA is issued.
Timeline
- Jan 25 '22
-
Feb 9 '22
PRS PRS Meeting by Webex OnlyPRSDeferred/Tabled Tabled Referred → ROS Referred → WMS“To table NPRR1118 and refer the issue to ROS and WMS” — Passed→ PRS for consideration
- Mar 2 '22
-
Mar 3 '22
ROS ROS Meeting by Webex Only“Request PRS continue to table NPRR1118 for further discussion at OWG”
- Mar 9 '22
-
Mar 24 '22
Listed without action at 15 meetings (Mar 24 '22 – Jun 9 '22)
- Jun 23 '22
-
Jul 13 '22
Listed without action at 2 meetings (Jul 13 '22 – Jul 26 '22)
- Aug 3 '22
- Aug 10 '22
-
Aug 11 '22
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Jun 13 '22 ERCOT comments“To recommend approval of NPRR1118 as amended by the 6/13/22 ERCOT comments as revised by PRS” — Passed→ PRS for Impact Analysis consideration
-
Sep 15 '22
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward to TAC the 8/11/22 PRS Report and 1/25/22 Impact Analysis for NPRR1118” — Passed→ TAC for consideration
-
Sep 28 '22
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR1118 as recommended by PRS in the 9/15/22 PRS Report” — Passed→ Board for consideration
-
Oct 18 '22
BOARD Board of Directors MeetingBOARDRecommended for Approval Recommended for approval“To recommend approval of NPRR1118 as recommended by TAC in the 9/28/22 TAC Report” — Passed→ PUCT for consideration
-
Nov 3 '22
PUCTPUCTApproved Approved“To approve NPRR1118 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization” — Passed