NPRR #1111 · Revision Request

NPRR1111  Related to SCR819, Improving IRR Control to Manage GTC Stability Limits

Approved Urgent sponsor ERCOT posted 2021-12-13 ercot.com
ReasonAddresses current operational issues
Created2021-12-14
Approved2022-03-31
Sections Affected
3.3.86.5.7.46.5.7.96.6.5.26.6.5.36.6.5.58.1.1.4.1
Summary
This Nodal Protocol Revision Request (NPRR) expands the use of the Security-Constrained Economic Dispatch (SCED) Base Point Below High Dispatch Limit (“SBBH”) flag to signify that ERCOT has instructed an Intermittent Renewable Resource (IRR) or Direct Current (DC)-Coupled Resources not to exceed its Base Point. These changes improve the control of IRRs in order to more efficiently manage Generic Transmission Constraint (GTC) stability limits. Additionally, the Base Point Deviation Charge threshold for IRRs is adjusted to encourage better SCED Base Point control.