NPRR #1109 · Revision Request

NPRR1109  Process for Reinstating Decommissioned Generation Resources

Approved Urgent sponsor ERCOT posted 2021-11-09 ercot.com
ReasonAddresses current operational issues; Market efficiencies or enhancements
Created2021-11-10
Approved2021-12-16
Sections Affected
3.14.1.9 and Section 22 Attachment H
Summary
This Nodal Protocol Revision Request (NPRR) allows a Resource Entity to bring a Decommissioned Generation Resource back to service if it submits a Notification of Change of Generation Resource Designation notifying ERCOT of the intended return to service within three years of the date the Generation Resource was removed from the ERCOT Network Operations Model. This NPRR gives ERCOT and the interconnecting Transmission and/or Distribution Service Provider (TDSP) discretion to require any needed studies testing, metering, or facility upgrades to ensure the reliable interconnection of the Generation Resource.
Timeline