NPRR #1106 · Revision Request
NPRR1106 Deployment of Emergency Response Service (ERS) Prior to Declaration of Energy Emergency Alert (EEA)
ReasonAddresses current operational issues; Market efficiencies or enhancements; Regulatory requirements
Created2021-11-10
Approved2021-12-16
Sections Affected
2.13.14.36.5.9.4.16.5.9.4.26.5.9.4.38.1.3.1.3.1and 8.1.3.1.3.2
Summary
This Nodal Protocol Revision Request (NPRR) revises the Protocols to allow for the deployment of ERS prior to the declaration of an EEA when Physical Responsive Capability (PRC) falls below 3,000 MW and is not projected to be recovered above 3,000 MW within 30 minutes following the deployment of Non-Spin.
Timeline
- Nov 4 '21
-
Nov 10 '21
PRS PRS Meeting by Webex OnlyPRSRecommended for Approval Urgent status Recommended for approval Forwarded → TAC“To waive notice for NPRR1106; to grant NPRR1106 Urgent status; to recommend approval of NPRR1106 as submitted, and to forward to TAC NPRR1106 and the Impact Analysis” — Passed→ Revision Request Consideration
- Nov 15 '21
-
Nov 17 '21
Listed without action at 1 meeting
-
Nov 29 '21
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval“to recommend approval of NPRR1106 as recommended by PRS in the 11/10/21 PRS Report with a recommended effective date of upon PUCT approval (12/17/21)” — Passed→ Revision Request Consideration
-
Dec 10 '21
BOARDEmail Vote / Unlisted MeetingBOARDRecommended for Approval Recommended for approval“to recommend approval of NPRR1106 as recommended by TAC in the 11/29/21 TAC Report” — Passed→ Revision Request Consideration
-
Dec 16 '21
PUCTPUCTApproved Approved“to approve NPRR1106 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307, Review of Rules Adopted by the Independent Organization in Calendar Year 2021” — Passed