NPRR1101  Create Non-Spin Deployment Groups made up of Generation Resources Providing Off-Line Non-Spinning Reserve and Load Resources that are Not Controllable Load Resources Providing Non-Spinning Reserve

Approved Urgent sponsor ERCOT posted 2021-10-20 ercot.com
ReasonAddresses current operational issues. Market efficiencies or enhancements
Created2021-11-10
Approved2021-12-16
Sections Affected
6.5.7.6.2.3
Summary
This NPRR modifies the deployment grouping requirements for Load Resources that are not Controllable Load Resources (“NCLRs”) providing Non-Spinning Reserve (Non-Spin) to include Generation Resources providing Off-Line Non-Spin. This deployment grouping process only addresses NCLR and Off-Line Generation Resources. Other Resources providing Non-Spin are not addressed in the proposed revisions.