NPRR1099  Managing Network Operations Model Resource Nodes

Approved sponsor ERCOT posted 2021-09-29 ercot.com
ReasonAddresses current operational issues; Market efficiencies or enhancements
Created2021-10-14
Approved2022-03-31
Sections Affected
3.10.3.1
Summary
This Nodal Protocol Revision Request (NPRR) grants ERCOT greater authority to move a Resource Node in the Network Operations Model when deemed necessary to properly reflect Point of Interconnection (POI) changes or Resource retirements.
Timeline