NPRR #1098 · Revision Request
NPRR1098 Direct Current Tie (DC Tie) Reactive Power Capability Requirements
ReasonRegulatory Requirements
Created2021-10-14
Approved2022-03-31
Sections Affected
2.13.15.13.15.4 (new)and 6.5.6
Summary
This Nodal Protocol Revision Request (NPRR) establishes Reactive Power capability requirements for new Direct Current Ties (DC Ties) interconnecting to the ERCOT System and existing DC Ties replaced after January 1, 2021.
Timeline
- Sep 29 '21
-
Oct 14 '21
PRS PRS Meeting by Webex OnlyPRSRecommended for Approval Recommended for approval“to recommend approval of NPRR1098 as submitted” — Passed→ Impact Analysis Consideration
-
Oct 15 '21
Listed without action at 1 meeting
- Oct 21 '21
- Nov 4 '21
-
Nov 10 '21
PRS PRS Meeting by Webex OnlyPRSDeferred/Tabled Tabled“To table NPRR1098” — Passed→ Impact Analysis Consideration
- Nov 18 '21
- Dec 2 '21
-
Dec 14 '21
PRS PRS Meeting by Webex OnlyPRSRecommended for Approval Recommended for approval Forwarded → TAC Amended by the Nov 29 '21 ERCOT comments priority 2022 · rank 2530“to endorse and forward to TAC the 11/10/21 PRS Report as amended by the 11/29/21 ERCOT comments and the Impact Analysis for NPRR1098 with a recommended priority of 2022 and rank of 2530” — Passed→ Revision Request Consideration
- Jan 6 '22
-
Jan 31 '22
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval“to recommend approval of NPRR1098 as recommended by PRS in the 12/14/21 PRS Report” — Passed→ Revision Request Consideration
-
Mar 7 '22
BOARD Board of Directors MeetingBOARDRecommended for Approval Recommended for approval“to recommend approval of NPRR1098 as recommended by TAC in the 1/31/22 TAC Report” — Passed→ Revision Request Consideration
-
Mar 31 '22
PUCTPUCTApproved Approved“to approve NPRR1098 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization” — Passed
-
—
Posted since the last meeting