NPRR #1093 · Revision Request
NPRR1093 Load Resource Participation in Non-Spinning Reserve
ReasonAddresses current operational issues / Meets Strategic goals (tied to the ERCOT Strategic Plan or directed by the ERCOT Board) / Market efficiencies or enhancements
Created2021-09-16
Approved2021-10-28
Sections Affected
3.6.13.9.13.17.34.4.7.24.4.7.2.16.4.9.1.36.5.5.26.5.7.3.16.5.7.6.2.36.7.58.1.1.2.1.3and 8.1.1.4.3
Summary
This Nodal Protocol Revision Request (NPRR) changes the Protocols to allow Load Resources that are not Controllable Load Resources to provide Non-Spin. The NPRR largely reinstates Protocol requirements that were in place during the first five years of the Nodal Market implementation that were subsequently changed to enable Controllable Load Resource participation in Security-Constrained Economic Dispatch (SCED) and Non-Spin. Additionally, it also incorporates market design changes that have been made for the Operating Reserve Demand Curve (ORDC) and Reliability Deployment Price Adder process when deploying Ancillary Services from Load Resources that are not Controllable Load Resources.
Timeline
- Sep 1 '21
-
Sep 16 '21
PRS PRS Meeting by Webex OnlyPRSRecommended for Approval Urgent status Recommended for approval Amended by the Sep 10 '21 ERCOT comments Forwarded → TAC priority 2021 · rank 3195“To grant NPRR1093 Urgent status; to recommend approval of NPRR1093 as amended by the 9/10/21 ERCOT comments as revised by PRS; and to forward to TAC NPRR1093 and the Impact Analysis with a recommended priority of 2021 and rank of 3195” — Passed→ TAC for consideration
-
Sep 29 '21
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval“To recommend approval of NPRR1093 as recommended by PRS in the 9/16/21 PRS Report; and the Revised Impact Analysis” — Passed→ Board for consideration
- Oct 19 '21
-
Oct 22 '21
BOARD Board of Directors Special MeetingBOARDRecommended for Approval Recommended for approval“To recommend approval of NPRR1093 as recommended by TAC in the 9/29/21 TAC Report” — Passed→ PUCT for consideration
-
Oct 28 '21
PUCTPUCTApproved Approved“To approve NPRR1093 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307, Review of Rules Adopted by the Independent Organization in Calendar Year 2021” — Passed
- Jan 21 '22
-
Feb 10 '22
Listed without action at 7 meetings (Feb 10 '22 – May 25 '22)