NPRR #1093 · Revision Request

NPRR1093  Load Resource Participation in Non-Spinning Reserve

Approved Urgent sponsor ERCOT posted 2021-09-01 ercot.com
ReasonAddresses current operational issues / Meets Strategic goals (tied to the ERCOT Strategic Plan or directed by the ERCOT Board) / Market efficiencies or enhancements
Created2021-09-16
Approved2021-10-28
Sections Affected
3.6.13.9.13.17.34.4.7.24.4.7.2.16.4.9.1.36.5.5.26.5.7.3.16.5.7.6.2.36.7.58.1.1.2.1.3and 8.1.1.4.3
Summary
This Nodal Protocol Revision Request (NPRR) changes the Protocols to allow Load Resources that are not Controllable Load Resources to provide Non-Spin. The NPRR largely reinstates Protocol requirements that were in place during the first five years of the Nodal Market implementation that were subsequently changed to enable Controllable Load Resource participation in Security-Constrained Economic Dispatch (SCED) and Non-Spin. Additionally, it also incorporates market design changes that have been made for the Operating Reserve Demand Curve (ORDC) and Reliability Deployment Price Adder process when deploying Ancillary Services from Load Resources that are not Controllable Load Resources.
Timeline