NPRR #1090 · Revision Request
NPRR1090 ERS Winter Storm Uri Lessons Learned Changes and Other ERS Items
ReasonMarket efficiencies or enhancements; Addresses current operational issues
Created2021-08-12
Approved2021-10-28
Sections Affected
2.13.14.3.13.14.3.36.5.9.4.28.1.3.1.3.18.1.3.1.3.28.1.3.1.3.38.1.3.1.48.1.3.28.1.3.3
Summary
This Nodal Protocol Revision Request (NPRR) makes a number of revisions pertaining to Emergency Response Service (ERS) that addresses items 48 and 102 of TAC’s Emergency Conditions List, including: 1) Modifying the requirement of issuing an Extensible Markup Language (XML) message followed by a Verbal Dispatch Instruction (VDI) for ERS deployments by using only the XML message and eliminating the VDI from the requirement; 2) Modifying and clarifying language related to the beginning and end of ERS Contract Periods for ERS renewals; 3) Removing the limit on the maximum number of deployments per ERS Contract Period, the three-hour maximum limit per single deployment event, and modifying language related to the cumulative deployment obligation time requirement for Weather-Sensitive ERS Resources; 4) Eliminating the options for ERS Resources to be excluded from an ERS deployment event or to exclude intervals from event and availability performance with properly noticed scheduled unavailability and planned maintenance for up to 2% of their obligated intervals without payment reductions; 5) Modifying language related to short ERS Contract Period availability calculations for ERS Resources to account for short Contract Periods in which no exhaustion occurs and modifying the formula for the ratio of Availability Factor Hours to the total awarded hours in the ERS Standard Contract Term to include all awarded hours in the Standard Contract Term; 6) Removing the requirement to reduce the time-weighting factor for intervals by 25% after eight hours for Qualified Scheduling Entity (QSE)-level event performance; 7) Removing language related to the first full interval of an ERS deployment event from the ERS Resource-level event performance criteria and modifying language related to successful performance during ERS deployment events to satisfy annual testing requirements; 8) Removing language related to testing ERS Generators for failing self-tests; and 9) Modifying QSE-level event performance to be both time and capacity weighted.
Timeline
- Jul 28 '21
- Jul 30 '21
-
Aug 12 '21
PRS PRS Meeting by Webex OnlyPRSDeferred/Tabled Tabled Referred → WMS“to table NPRR1090 and refer the issue to WMS” — Passed→ Language Consideration
-
Sep 1 '21
WMS WMS Meeting by Webex Only“To endorse Urgent status for NPRR1090; to endorse NPRR1090 as revised by WMS”
-
Sep 16 '21
PRS PRS Meeting by Webex OnlyPRSRecommended for Approval Urgent status Amended by the Sep 7 '21 WMS comments Recommended for approval Forwarded → TAC priority 2021 · rank 3360“to grant NPRR1090 Urgent status; to recommended approval of NPRR1090 as amended by the 9/7/21 WMS comments as revised by PRS; and to forward to TAC NPRR1090 and the Impact Analysis with a recommended priority of 2021 and rank of 3360” — Passed→ Revision Request Consideration
-
Sep 29 '21
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval“to recommend approval of NPRR1090 as recommended by PRS in the 9/16/21 PRS Report; and the Revised Impact Analysis” — Passed→ Revision Request Consideration
-
Oct 22 '21
BOARD Board of Directors Special MeetingBOARDRecommended for Approval Recommended for approval“to recommend approval of NPRR1090 as recommended by TAC in the 9/29/21 TAC Report” — Passed→ Revision Request Consideration
-
Oct 28 '21
PUCTPUCTApproved Approved“To approve NPRR1090 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307, Review of Rules Adopted by the Independent Organization in Calendar Year 2021” — Passed
- Apr 26 '24