NPRR #1082 · Revision Request

NPRR1082  Emergency Response Service (ERS) Test Exception for Co-located ERS Loads

Approved sponsor Enerwise Global Technologies posted 2021-06-22 ercot.com
ReasonAddresses current operational issues; Market efficiencies or enhancements
Created2021-07-15
Approved2021-10-28
Sections Affected
8.1.3.2
Summary
This Nodal Protocol Revision Request (NPRR) changes the testing criteria for Emergency Response Service (ERS) Load with obligations no greater than 100 kW that is co-located with an ERCOT Generator. If the ERS Load and ERS Generator are evaluated separately, the ERS Load will be considered to have passed its testing obligations if the ERS Generator meets the combined testing obligations of both the ERCOT Generator and the ERS Load.