NPRR #1073 · Revision Request
NPRR1073 Market Entry/Participation by Principals of Counter-Parties with Financial Obligations
ReasonAddresses current operational issues, Market efficiencies and enhancements
Created2021-04-15
Approved2021-08-19
Sections Affected
16.1.2 (new)16.2.116.2.1.1 (new)16.2.1.116.2.216.2.2.216.2.2.316.2.3.216.8.116.8.1.1 (new)16.8.216.8.2.216.8.2.316.8.3.1Section 23 Form ASection 23 Form GERCOT Fee Schedule
Summary
This Nodal Protocol Revision Request (NPRR) modifies ERCOT’s market entry qualification and continued participation requirements for ERCOT Counter-Parties i.e., Qualified Scheduling Entities (QSEs) and Congestion Revenue Right (CRR) Account Holders, and modifies application forms for QSEs and CRR Account Holders. This NPRR makes the following modifications to Section 16, Registration and Qualification of Market Participants: (1) Defines Principals of a Market Participant; and (2) Provides that a QSE/CRR Account Holder applicant or existing QSE/CRR Account Holder must be able to demonstrate to ERCOT’s reasonable satisfaction that its Principals were/are not Principals of a terminated Market Participant with money remaining owed to ERCOT. This NPRR also modifies the QSE/CRR Account Holder applicant form to require disclosure of the Principals of the QSE/CRR Account Holder applicant.
Timeline
-
Apr 5 '21
PRSFiled by Morgan Stanley Capital Group Inc
-
Apr 15 '21
PRS PRS Meeting by Webex OnlyPRSRecommended for Approval Urgent status Recommended for approval Amended by the Apr 14 '21 DC Energy comments Forwarded → TAC“to grant NPRR1073 Urgent status; to recommend approval of NPRR1073 as amended by the 4/14/21 DC Energy comments; and to forward to TAC” — Passed→ Revision Request Consideration
-
Apr 21 '21
CREDITWG CWG/MCWG Meeting by Webex Only
-
Apr 28 '21
TAC TAC Meeting by Webex OnlyTACDeferred/Tabled Tabled“to table NPRR1073” — Passed→ Revision Request Consideration
-
May 26 '21
TAC TAC Meeting by Webex OnlyTACDeferred/Tabled Tabled Referred → WMS“to table NPRR1073 until the July 28, 2021 TAC meeting, and to refer the issue to WMS” — Passed→ Revision Request Consideration
-
Jun 2 '21
WMS WMS Meeting by Webex Only“Request TAC continue to table NPRR1073 for further review by MCWG and an ERCOT workshop re securitization”
- Jun 23 '21
- Jul 7 '21
- Jul 21 '21
-
Jul 28 '21
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval Amended by the Jul 6 '21 Luminant comments“to recommend approval of NPRR1073 as recommended by PRS in the 4/15/21 PRS Report as amended by the 7/6/21 Luminant comments; and the Revised Impact Analysis” — Passed→ Revision Request Consideration
-
Aug 10 '21
BOARD Urgent Board of Directors Meeting – Teleconference Available by WebcastBOARDRecommended for Approval Recommended for approval“To recommend approval of NPRR1073 as recommended by TAC in the 7/28/21 TAC Report” — Passed→ PUCT for consideration
-
Aug 19 '21
PUCTPUCTApproved Approved“to approve NPRR1073 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307” — Passed
- Nov 3 '21