NPRR1062  Modify IDR Meter Requirement and Eliminate IDR Meter Requirement Report

Approved sponsor ERCOT posted 2021-01-15 ercot.com
ReasonAddresses current operational issues; Market efficiencies or enhancements
Created2021-02-11
Approved2021-06-08
Sections Affected
2.110.2.210.3.3.310.918.618.6.118.6.2 (delete)18.6.3 (delete)18.6.4 (delete)18.6.5 (delete)18.6.6 (delete)18.7 (new)
Summary
This Nodal Protocol Revision Request (NPRR) changes the metering requirement for Premises connected at transmission voltage and/or having a peak Demand greater than 700kW/700kVA. Currently an Interval Data Recorder (IDR) Meter is required. This change modifies the requirement to be an IDR which includes IDR Meters and Advanced Meters. This NPRR also eliminates the IDR Meter Requirement Report.