ERCOT·WATCH Search ercot.com  ⌕
NPRR #1042 · Revision Request

NPRR1042  Planned Capacity Adjustment in the Report on Capacity, Demand and Reserves in the ERCOT Region

Approved sponsor Reliant Energy Retail Services posted 2020-08-26 ercot.com
ReasonAddresses current operational issues
Created2020-09-10
Approved2020-12-08
Sections Affected
3.2.6.2.2
Summary
This Nodal Protocol Revision Request (NPRR) adjusts the planned capacity in the Report on Capacity, Demand and Reserves in the ERCOT Region to remove previously mothballed or retired Generation Resources that may be repowered but do not have an owner that intends to operate them.
Timeline