NPRR #1037 · Revision Request

NPRR1037  Correction to the Settlement of Switchable Generation Resources (SWGRs) Instructed to Switch to ERCOT

Approved sponsor ERCOT posted 2020-07-29 ercot.com
ReasonAddresses current operational issues
Created2020-08-13
Approved2020-10-13
Sections Affected
6.6.12.1
Summary
This Nodal Protocol Revision Request (NPRR) provides a correction to the settlement of Switchable Generation Resources (SWGRs) when instructed by ERCOT to switch from a non-ERCOT Control Area to the ERCOT Control Area. Specifically, this NPRR includes “Operational Costs” (“OPCs”) incurred by the SWGR in the non-ERCOT Control Area in the calculation of the “Switchable Generation Operating Cost” (“SWOC”) for Resources with approved verifiable costs. OPC is currently included only for Resources without approved verifiable costs.
Timeline