NPRR #103 · Revision Request
NPRR103 Settlement of Power Imported via DC Ties and Block Load Transfer Under a Declared Emergency Condition
ReasonThe additions to the Settlement formulas included in this Nodal Protocol Revision Request (NPRR) are intended to make the QSE responsible for responding to the ERCOT Dispatch Instructions issued during a declared Emergency Condition an assured cost recovery. Charges to cover the payments described in this NPRR are included in Section 6.6.10, Real-Time Revenue Neutrality Allocation.
Created2008-02-21
Approved2008-04-15
Sections Affected
6.6.3.4Real-Time Energy for DC Tie Import 6.6.3.5Real-Time Payment for a Block Load Transfer Point
Summary
These revisions add Settlement formulas to pay a Qualified Scheduling Entity (QSE) for emergency energy imported over the DC Ties and for energy supplied to BLT Load moved from the ERCOT control area to a Non-ERCOT control area during a declared Emergency Condition. These payments may only be made for actions taken by the (QSE) in response to an ERCOT Dispatch Instruction.
Timeline
- Feb 13 '08
-
Feb 21 '08
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the ERCOT comments Amended by the PRS comments“To recommend approval of NPRR103 as revised by ERCOT comments and PRS.” — Passed→ PRS review of the Impact Analysis and Recommendation Report.
-
Mar 20 '08
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Mar 19 '08 ERCOT Staff comments Forwarded → TAC“To recommend approval of NPRR103 as revised by ERCOT Staff comments dated 3/19/08 and forward the IA and this Recommendation Report to TAC.” — Passed→ TAC review of NPRR103.
-
Apr 4 '08
TAC TAC MeetingTACRecommended for Approval Recommended for approval“Recommend approval of NPRR103 as recommended by PRS.” — Passed→ ERCOT Board consideration of NPRR103.
-
Apr 15 '08
BOARD Board of Directors MeetingBOARDApproved Recommended for approval“Approved as recommended by TAC.” — Passed
-
—