NPRR #1009 · Revision Request
NPRR1009 RTC – NP 5: Transmission Security Analysis and Reliability Unit Commitment
ReasonMeets Strategic goals. Market efficiencies or enhancements. Regulatory requirements.
Created2020-06-11
Approved2020-12-08
Sections Affected
5.15.2.2.15.2.2.25.35.45.4.1 (new)5.5.25.6.25.7.1.35.7.1.45.7.4.1.1and 5.8
Summary
This Nodal Protocol Revision Request (NPRR) updates Transmission Security Analysis and Reliability Unit Commitment (RUC) to address changes associated with the implementation of Real-Time Co-optimization (RTC) of energy and Ancillary Services.
Timeline
- Mar 25 '20
-
Apr 8 '20
Listed without action at 6 meetings (Apr 8 '20 – Jun 10 '20)
- Jun 11 '20
- Jun 29 '20
- Jul 16 '20
-
Jul 22 '20
Listed without action at 7 meetings (Jul 22 '20 – Oct 21 '20)
-
Nov 11 '20
PRS PRS Meeting by Webex OnlyPRSRecommended for Approval Urgent status Recommended for approval Amended by the Oct 23 '20 ERCOT comments Forwarded → TAC“To grant NPRR1009 Urgent status; to recommend approval of NPRR1009 as amended by the 10/23/20 ERCOT comments; and to forward to TAC NPRR1009 and the Impact Analysis” — Passed→ TAC for consideration
-
Nov 18 '20
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval“To recommend approval of NPRR1009 as recommended by PRS in the 11/11/20 PRS Report” — Passed→ Board for consideration
-
Dec 8 '20
BOARD Urgent Board of Directors Meeting – Teleconference Available by WebcastBOARDApproved Recommended for approval“To approve NPRR1009 as recommended by TAC in the 11/18/20 TAC Report” — Passed
-
—
Posted since the last meeting