NPRR #1005 · Revision Request
NPRR1005 Clarify Definition of Point of Interconnection (POI) and Add Definition Point of Interconnection Bus (POIB)
ReasonAddresses current operational issues; Market efficiencies or enhancements
Created2020-06-11
Approved2021-08-19
Sections Affected
2.12.23.2.6.2.23.10.3.13.10.7.23.10.7.33.10.7.5.23.153.15.13.15.26.5.7.710.3.2.3and 23K
Summary
This Nodal Protocol Revision Request (NPRR) proposes the following revisions: • Revises the definition of Point of Interconnection (POI) to refer to any physical location where a Generation Entity’s Facilities connect to a Transmission Service Provider’s (TSP’s) Facilities, and removes references to Load interconnections, since the only relevant Load connection points are those associated with the Generation Entity’s generators, which are included in the term “Generation Entity’s Facilities.” • Introduces the term “Point of Interconnection Bus (POIB)” to refer to the Electrical Bus in the substation that is closest to the Generation Resource’s POI, or any electrically equivalent Electrical Bus in that substation, for each TSP-owned substation to which the Generation Resource interconnects. • Changes POI to POIB throughout the Protocols in appropriate cases based on the above clarifications. • Removes the reference to POI in Section 2.1 in the definition of Aggregate Generation Resource because having a common Generator Step Up (GSU) transformer would aggregate output before the POI, and the generators’ separate outputs do not have separate POIs. • Clarifies Section 10.3.2.3 to specify that, at a given Generation Resource Facility, generation and associated Load must either be physically metered at each POI or Service Delivery Point, or loss-compensated to the applicable POI in accordance with Section 10.3.2.2. • Adds NPRR917, Nodal Pricing for Settlement Only Distribution Generators (SODGs) and Settlement Only Transmission Generators (SOTGs), greyboxed language to Section 10.3.2.3 and removes the greybox, as there is no system implementation required for language in Section 10.3.2.3. • Removes POI from Section 23, Form K because it is used there incorrectly.
Timeline
- Feb 26 '20
-
Mar 25 '20
Listed without action at 6 meetings (Mar 25 '20 – Jun 4 '20)
- Jun 11 '20
- Jun 18 '20
-
Jul 9 '20
Listed without action at 14 meetings (Jul 9 '20 – Jan 27 '21)
- Feb 11 '21
- Mar 11 '21
-
Mar 24 '21
Listed without action at 1 meeting
- Apr 15 '21
-
Apr 28 '21
Listed without action at 1 meeting
-
May 13 '21
PRS PRS Meeting by Webex OnlyPRSRecommended for Approval Recommended for approval Amended by the Apr 7 '21 Longhorn Power comments“to recommend approval of NPRR1005 as amended by the 4/7/21 Longhorn Power comments as revised by PRS” — Passed→ Impact Analysis Consideration
- May 26 '21
-
Jun 10 '21
PRS PRS Meeting by Webex OnlyPRSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 5/13/21 PRS Report and Impact Analysis for NPRR1005” — Passed→ Revision Request Consideration
-
Jun 23 '21
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval“to recommend approval of NPRR1005 as recommended by PRS in the 6/10/21 PRS Report” — Passed→ Revision Request Consideration
-
Aug 10 '21
BOARD Urgent Board of Directors Meeting – Teleconference Available by WebcastBOARDRecommended for Approval Recommended for approval“to recommend approval of NPRR1005 as recommended by TAC in the 6/23/21 TAC Report” — Passed→ PUCT for consideration
-
Aug 19 '21
PUCTPUCTApproved Approved“to approve NPRR1005 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307” — Passed
-
—
Posted since the last meeting