NPRR #96 · Revision Request
NPRR096 Revisions to the RMR Startup Energy Payment
ReasonThe Nodal Protocols need provisions for the determination of eligibility for compensation for startup costs in the event of multiple starts in a day from the Day Ahead Market (DAM) and Reliability Unit Commitment (RUC) markets.
Created2008-01-17
Approved2008-03-18
Sections Affected
6.6.6.2RMR Payment for Energy
Summary
This Nodal Protocol Revision Request (NPRR) incorporates language from the COMS Eligibility Process for Settlements Requirements (B2) (v3.0) (Eligibility Process) document approved by the Transition Plan Task Force (TPTF) on October 8, 2007. The proposed language is consistent with the language in the Eligibility Process to determine if a Reliability Must Run (RMR) Unit is to be compensated for its startup costs as well as Protocol Sections 5.6.2, RUC Startup Cost Eligibility, and 5.6.3, Forced Outage of a RUC-Committed Resource.
Timeline
-
Jan 7 '08
PRSFiled by ERCOT Staff
-
Jan 17 '08
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of this NPRR as submitted.” — Passed→ Review of the Impact Analysis and Recommendation Report for NPRR096.
-
Feb 21 '08
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To forward the Impact Analysis and Recommendation Report to TAC.” — Passed→ TAC consideration of NPRR096
-
Mar 6 '08
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval as recommended by PRS.” — Passed→ ERCOT Board consideration of NPRR096
-
Mar 18 '08
BOARD Board of Directors MeetingBOARDApproved Recommended for approval“Approve NPRR096 as recommended by TAC.” — Passed