NPRR #82 · Revision Request
NPRR082 Section 8, Performance Monitoring and Compliance, Revisions to Monitoring and Qualification Tests
ReasonIn the current zonal market design, both Responsive Reserve and Non-Spin are deployed as energy by the Load Frequency Control (LFC) system. In the Texas Nodal Market LFC will notify QSEs to make its reserved capacity available to SCED which results in Base Points that effectively deploys RRS and Non-spin energy as needed by the system. The monitoring and qualification methods described in Section 8 need to be updated to be compatible with this approach.
Created2007-09-20
Approved2007-12-11
Sections Affected
8.1.2.2.38.1.2.2.48.1.2.4.28.1.2.4.3
Summary
This NPRR makes the testing and compliance requirements consistent with NPRR049, Generation Subsystem Changes to Incorporate Approved Whitepapers, and the white papers "Generation Resource Responsive Reserve Deployment and Recall" and "Non-Spin Deployment Notification and Availability" approved by TPTF located at http://nodal.ercot.com/docs/pd/mms/index.html#oth.
Timeline
- Sep 11 '07
-
Sep 20 '07
PRS PRS MeetingPRSRemanded Remanded → TPTF“On 9/20/07, PRS voted to remand NPRR082 to TPTF to consider the comments of Occidental Chemical Corporation and whether to integrate NPRR082 with the overhaul of Section 8, Performance Monitoring and Compliance. There was one opposing vote and one abstention, both from the Independent Power Marketer Market Segment. All Market Segments were present for the vote.” — Passed
-
Sep 24 '07
Listed without action at 1 meeting
-
Sep 25 '07
TPTFEmail Vote / Unlisted MeetingTPTFRecommended for Approval Action → PRS“To submit comments to PRS.” — Passed→ Language review
-
Oct 18 '07
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the TPTF comments“To recommend approval of NPRR082 as revised by TPTF comments.” — Passed→ Impact Analysis review
-
Nov 15 '07
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To forward NPRR082 and its IA to TAC.” — Passed→ TAC consideration
-
Nov 29 '07
TAC TAC MeetingTACRecommended for Approval Recommended for approval Amended by the TAC comments“To recommend approval of NPRR082 as revised by TAC.” — Passed→ Board consideration
-
Dec 11 '07
BOARD Board of Directors MeetingBOARDApproved Approved“To approve NPRR082 as recommended by TAC.” — Passed
-
—
Posted since the last meeting