NPRR #76 · Revision Request
NPRR076 Synchronization of Emergency Electric Curtailment Plan (EECP) Event Realignment
ReasonThis revision implements the changes to EECP Steps to allow earlier communication of reliability concerns by ERCOT to Market Participants (MPs) and concerned entities.
Created2007-07-19
Approved2007-12-11
Sections Affected
2.12.26.5.7.56.5.9.46.5.9.4.1 (new)6.5.9.4.1
Summary
This Nodal Protocol Revision Request (NPRR) synchronizes the Nodal Protocols with PRR682, EECP Event Realignment, which was approved by the ERCOT Board on November 14, 2006.
Timeline
- Jul 2 '07
-
Jul 19 '07
PRS PRS MeetingPRSRemanded Remanded → WMS“Remand NPRR076 to WMS and direct that the Demand Side Working Group (DSWG) further review the Load Resource selection process in Section 6.5.9.4.1, EECP Steps.” — Passed
- Aug 13 '07
- Aug 23 '07
-
Sep 20 '07
PRS PRS MeetingPRSDeferred/Tabled Tabled“To table further consideration of NPRR076 until the October PRS meeting to allow for additional comments.” — Passed→ PRS consideration of NPRR076
- Oct 17 '07
-
Oct 18 '07
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the DSWG comments“Recommend approval of NPRR076 as revised by DSWG comments.” — Passed→ Review of Impact Analysis
-
Nov 15 '07
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To forward the Recommendation Report and IA to TAC.” — Passed
-
Nov 29 '07
TAC TAC MeetingTACRecommended for Approval Recommended for approval Action“Recommend approval of NPRR076 and to instruct ERCOT to design the Nodal system in such a way to allow the RDF to be reduced to zero.” — Passed
-
Dec 11 '07
BOARD Board of Directors MeetingBOARDApproved Recommended for approval“Approve NPRR076 as recommended by TAC” — Passed
-
—
Posted since the last meeting