NPRR #69 · Revision Request
NPRR069 Changes to SURAMP
ReasonUnder NPRR049, Generation Subsystem Changes to Incorporate Approved Whitepapers, SCED will deploy RRS energy instead of LFC. Hence the Ramp Rate needed for RRS deployment should be allotted to SCED, as proposed in this NPRR.
Created2007-06-21
Approved2007-07-17
Sections Affected
6.5.7.2Resource Limit Calculator
Summary
This NPRR revises the Security Constrained Economic Dispatch (SCED) Up Ramp Rate (SURAMP) formulation. This change removes reserving part of Ramp Rate for Responsive Reserve Service (RRS) deployment by Load Frequency Control (LFC)
Timeline
- Jun 15 '07
-
Jun 21 '07
TPTF TPTF MeetingPRSRecommended for Approval Amended by the TPTF comments Recommended for approval Forwarded → TAC“To recommend approval of NPRR069 as amended by TPTF comments, endorse the IA and forward documents to TAC.” — Passed→ TAC considerations
-
Jun 28 '07
TACEmail Vote / Unlisted MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR069 and endorse the Baseline 2 IA as recommended by PRS.” — Passed→ Board consideration of NPRR and IA.
-
Jul 17 '07
BOARDEmail Vote / Unlisted MeetingBOARDApproved Recommended for approval“Approve NPRR072 as recommended by TAC” — Passed
- Aug 13 '07
-
—
Posted since the last meeting