ERCOT·WATCH Search ercot.com  ⌕
NPRR #52 · Revision Request

NPRR052  Settlement for Non-Modeled Generators

Approved sponsor TPTF posted 2007-03-12 ercot.com
ReasonSettlement of energy produced by Non-Modeled Generators is not addressed explicitly in the Protocols.
Created2007-03-22
Approved2007-07-17
Sections Affected
6.6.3.2Real-Time Energy Imbalance Payment or Charge at a Load Zone
Summary
Revise Real-time Energy Imbalance settlement to include payment of energy produced by Non-Modeled Generators