NPRR #50 · Revision Request

NPRR050  Clarifications for HSL Values for WGRs and WGR Values to be Used in the RUC Capacity Short Calculation

Approved sponsor Trip Doggett on behalf of TPTF posted 2007-03-12 ercot.com
ReasonThis NPRR will correct an inconsistency in the Protocols and clarify WGRs values to be used in the RUC capacity short calculation.
Created2007-03-22
Approved2007-07-17
Sections Affected
4.2.25.7.4.1.1
Summary
The proposed clarifications: 1) Eliminate 4.2.2(6) because of inconsistency with Protocol language in 3.9.1(7), Current Operating Plan (COP) Criteria ("A QSE representing a Wind-Powered Generation Resource (WGR) must enter an HSL value that is less than or equal to the amount for that Resource from the most recent Wind-Powered Generation Resource Production Potential provided by ERCOT"); 2) Eliminate 4.2.2(7) because the settlement information is described in 5.7.4.1, Capacity Shortfall Ratio Share; and 3) Revise 5.7.4.1.1 to clarify how to do the settlements.