NPRR #40 · Revision Request
NPRR040 Synchronization of Emergency Electric Curtailment Plan (EECP) Event Realignment
ReasonThis revision implements the changes to EECP Steps to allow earlier communication of reliability concerns by ERCOT to Market Participants (MPs) and concerned entities.
Created2007-02-16
Sections Affected
2.16.5.9.5.46.5.9.4.16.5.9.4.1
Summary
This NPRR synchronizes the Nodal Protocols with PRR682, EECP Event Realignment, which was approved by the ERCOT Board on November 14, 2006.
Timeline
-
Feb 16 '07
PRSFiled by Operating Guides Revision Task Force
-
Mar 5 '07
Listed without action at 8 meetings (Mar 5 '07 – Jun 25 '07)
- Jul 19 '07
-
Aug 2 '07
Listed without action at 1 meeting