NPRR #35 · Revision Request
NPRR035 Nodal Protocol Clarifications Required For Net Metering Provisions
ReasonThese changes are required to port the existing net metering provisions of the zonal market to the nodal market implementation. Additionally, these changes clarify that Generation Resource’s must provide net generation output for use by the ERCOT systems.
Created2006-11-28
Approved2007-07-17
Sections Affected
1.3.1.13.7.1.16.5.5.26.6.3.110.3.2.3
Summary
Revision to Protocol Section 1.3.1.1(w) adds the submittals to ERCOT by affected Entities that are required under the provisions of Protocol Section 10.3.2.3. This change captures as protected information the descriptions of the metering facilities of all Common Switchyards that contain multiple points of interconnection of Loads (ESIDs) and generation meters (EPS). Revisions to Protocol Section 3.7.1.1 add the requirement to include within the Resource Parameters submittal the methodology and, if utilized, the values of constants in any underlying net injection calculation for each Resource. Revision to Protocol Section 6.5.5.2 clarifies that net power output from generation resources may be provided to ERCOT systems as a measured or calculated value. Revisions to Protocol Section 6.6.3.1, Real-Time Energy Imbalance Payment or Charge at a Resource Node incorporate settlement methodology to be applied in the situation of a net metering installation. Revisions to Protocol Section 10.3.2.3: memorializes the requirement that affected entities provide to ERCOT metering diagrams; and adds the requirement that all Load(s) included in a net metering arrangement for an EPS Metering Facility shall only be electrically connected to the ERCOT grid through the EPS Metering point(s) for such Facility and that these Loads shall not be electrically connected to the ERCOT Grid through electrical connections that are not metered by the EPS metering point(s) for the Facility.
Timeline
- Nov 6 '06
-
Nov 28 '06
TPTF TPTF MeetingTPTFRecommended for Approval Recommended for approval Amended by the ERCOT comments Amended by the TPTF comments“To recommend approval of NPRR035 as revised by ERCOT comments and TPTF.” — Passed→ Language consideration
- Dec 14 '06
- Jan 22 '07
- Feb 5 '07
-
Feb 22 '07
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Feb 14 '07 ERCOT Staff comments“To recommend approval of NPRR035 as amended by ERCOT Staff comments [dated 2/14/07].” — Passed→ Impact Analysis review
-
May 17 '07
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the May 9 '07 ERCOT Staff comments“To recommend approval of NPRR035 as revised by ERCOT Staff comments dated 5/9/07.” — Passed→ Impact Analysis review
-
Jun 12 '07
PRS PRS and TPTF: Joint MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of B1G2 Impact Analysis” — Passed→ Review of B1G2 Impact Analysis
-
Jun 28 '07
TACEmail Vote / Unlisted MeetingTACRecommended for Approval Recommended for approval“To recommend approval of this NPRR and its IA as recommended by PRS.” — Passed→ Board consideration of this NPRR and its IA
-
Jul 17 '07
BOARDEmail Vote / Unlisted MeetingBOARDApproved Recommended for approval“To approve NPRR035 as recommended by TAC.” — Passed
-
—
Posted since the last meeting