NPRR #19 · Revision Request
NPRR019 Black Start Testing Requirements
ReasonERCOT's practice of conducting next start Resource tests when new next start Resources are selected is not documented. Also, the Protocols are unclear as to which tests may be conducted simultaneously.
Created2006-11-16
Approved2006-12-12
Sections Affected
8.1.2.2.6
Summary
Specifies the requirements for starting the next start Resource; Specifies which tests are allowed to be run simultaneously.
Timeline
- Aug 23 '06
- Sep 21 '06
- Oct 19 '06
-
Oct 24 '06
Listed without action at 1 meeting
-
Nov 16 '06
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the ERCOT comments“Recommend approval of NPRR019 with ERCOT’s comments.” — Passed
-
Dec 1 '06
TAC TAC MeetingTACRecommended for Approval Recommended for approval“Recommend approval of NPRR019 as recommended by PRS.” — Passed
-
Dec 12 '06
BOARD ERCOT Board of Directors MeetingBOARDApproved Approved“Approve NPRR019 as recommended by TAC.” — Passed→ Upon Texas Nodal market implementation
-
Jun 12 '07
PRS PRS and TPTF: Joint MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse the B1G1 IAs and forward the documents to TAC.” — Passed→ TAC review of Baseline 1 Group 1 Impact Analysis
- Jun 28 '07