NPRR #8 · Revision Request
NPRR008 PRR 307 Inclusion in Nodal
ReasonTo date PRR 307 has not been included in all areas of the Nodal Protocols to make it possible for qualified Controllable Load Resources to participate. At the June 7, 2006 PUC Open Meeting the Commissioners directed the inclusion of PRR 307 in the Nodal Protocols and in the subsequent software design. This NPRR makes the necessary corrections to meet the direction of the PUC.
Created2006-07-20
Approved2007-07-17
Sections Affected
23.7.1.23.9.13.163.17.24.4.7.26.3.26.5.5.26.5.7.56.5.7.6.16.5.7.6.2.28.1.2.28.1.2.2.28.1.2.3.28.1.2.4
Summary
Revise the necessary section of the Nodal Protocols to ensure that PRR 307 has been included.
Timeline
- Jul 17 '06
-
Jul 20 '06
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of NPRR008 as submitted.” — Passed→ TAC review
-
Aug 3 '06
TAC TAC MeetingTACRecommended for Approval Recommended for approval Referred → ROS“To recommend approval of NPRR008 as recommended by PRS; TAC also asked ROS to develop the comparable and appropriate standards and criteria to ensure performance of Loads providing these services.” — Passed→ Board consideration
-
Aug 15 '06
BOARD ERCOT Board of Directors MeetingBOARDApproved Approved“On 8/15/06, the Board voted to approve NPRR008 as recommended by TAC.” — Passed
-
Jun 12 '07
PRS PRS and TPTF: Joint MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“Endorse the B1G10 IA as revised by PRS and forward the document to TAC.” — Passed→ Review of B1G10 Impact Analysis
-
Jun 28 '07
TACEmail Vote / Unlisted MeetingTACRecommended for Approval Recommended for approval“Recommend approval of the B1G10 IA as recommended by PRS.” — Passed→ Consideration of revised IA.
-
Jul 17 '07
BOARDEmail Vote / Unlisted MeetingBOARDApproved Recommended for approval“To approve the B1G10 Impact Analysis as recommended by TAC.” — Passed
-
—
Posted since the last meeting