ERCOT·WATCH Search ercot.com  ⌕
NPRR #4 · Revision Request

NPRR004  Section 8, Zonal PRR Synchronization and ERCOT Staff Clarifications

Approved sponsor TPTF posted 2006-05-19 ercot.com
  1. PRS Jun 22 '06
  2. TAC Jul 6 '06
  3. BOARD Jul 18 '06
  4. PUCT —
ReasonTo incorporate into the Draft Nodal Protocols provisions approved by the Board for the Zonal market and determined by the ERCOT stakeholders to be relevant to the Nodal market.
Created2006-06-22
Approved2006-07-18
Sections Affected
8
Summary
This NPRR incorporates relevant language from the following PRRs that were approved by the Board between April 2004 and February 2006: PRR468, Frequency Response Requirements and Monitoring; PRR487, Black Start Resources; PRR490, LaaR Annual Testing Description; PRR535, Reactive Testing; PRR542, Clarifying the LaaR Three-Hour Limit; PRR628, ERCOT Operation Performance “ Non-Spinning Reserve Service Deployments; and PRR644, Ancillary Service Re-qualification. This NPRR also incorporates TPTF determinations regarding ERCOT Staff clarification questions as discussed by TPTF and documented in the ERCOT Clarification Matrix for Section 8 on and discussed at the TPTF meeting on 1/9/06.
Timeline