NPRR #2 · Revision Request
NPRR002 Section 3, Zonal PRR Synchronization and ERCOT Staff Clarifications
ReasonTo incorporate into the Draft Nodal Protocols provisions approved by the Board for the Zonal market and determined by the ERCOT stakeholders to be relevant to the Nodal market.
Created2006-06-22
Approved2007-07-17
Sections Affected
3
Summary
This NPRR incorporates relevant language from the following PRRs that were approved by the Board between April 2004 and February 2006: PRR492, Plan to Alleviate Chronic Local Congestion; PRR513, Verification of Operational Model after Recurring Local Congestion Event; PRR576, Disclosure of OOME, OOMC, and RMR Service; PRR596, Mothballed Generation Resource Estimated Return to Service Dates/PRR573, Mothballed Generation Resource Definition and Time to Service Updates; PRR581, Update RMR Language Due to PUC Rule 25.502; PRR627, RMR Transmission Issues and RMR Contract Extension; and PRR633, TSP Data Information Requirements. PRR307, Controllable Resources, was part of the TNT synchronization because a portion of the PRR language in the current zonal protocols was inadvertently not included in the nodal protocols section 3.17.2(2). This NPRR also incorporates TPTF determinations regarding ERCOT Staff clarification questions as documented in the ERCOT Clarification Matrix for Section 3 and discussed by TPTF and 3/29/06, 4/10/06 and 4/11/06.
Timeline
- May 19 '06
-
Jun 22 '06
PRS PRS MeetingPRSReferred Referred → TPTF Referred → ROS“Refer to TPTF and ROS to review NDSWG and ERCOT Staff comments.” — Passed→ TPTF and ROS review.
-
Jul 10 '06
Listed without action at 1 meeting
-
Jul 11 '06
TPTFEmail Vote / Unlisted MeetingTPTFRecommended for Approval→ PRS review
-
Jul 20 '06
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the TPTF comments“To recommend approval as ammended by TPTF.” — Passed→ TAC review
-
Aug 3 '06
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval as recommended by PRS.” — Passed→ Board consideration
-
Aug 15 '06
BOARD ERCOT Board of Directors MeetingBOARDApproved Approved“On 8/15/06, the Board voted to approve NPRR002 as recommended by TAC” — Passed
-
Jun 12 '07
PRS PRS and TPTF: Joint MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“Endorse the B1G6 IA as revised by PRS and forward the document to TAC for approval.” — Passed→ Review of B1G6 Impact Analysis
-
Jun 28 '07
TACEmail Vote / Unlisted MeetingTACRecommended for Approval Recommended for approval“Recommend approval of the B1G6 IA as recommended by PRS.” — Passed→ Review of B1G6 Impact Analysis
-
Jul 17 '07
BOARDEmail Vote / Unlisted MeetingBOARDApproved Recommended for approval“To approve the B1G6 Impact Analysis as recommended by TAC.” — Passed
-
—
Posted since the last meeting