NOGRR #289 · Revision Request

NOGRR289  Extension for LCL Cooling Load Ride-Through Compliance

Pending sponsor SB Energy posted 2026-07-21 sits at ROS next action Consideration then to TAC ercot.com
ReasonGeneral system and/or process improvement(s)
Created2026-07-21
Sections Affected
2.6.4 and 2.15
Summary
This Nodal Operating Guide Revision Request (NOGRR) permits a Large Computational Load (LCL) to achieve compliance with the applicable ride-through requirements within 365 days after its in-service date where the LCL’s cooling load is unable to satisfy such requirements as of the in-service date due to ongoing design and manufacturing limitations, including constraints associated with vendors’ continued adaptation of chiller and Variable Frequency Drive (VFD) equipment to the applicable standards.