NOGRR #282 · Revision Request

NOGRR282  Board Priority - Large Computational Load Ride-Through Requirements

Approved Urgent sponsor ERCOT posted 2025-11-14 ercot.com
ReasonStrategic Plan Objective 1
Created2025-12-04
Approved2026-07-09
Sections Affected
2.6.4 (new) and 2.14 (new)
Summary
This Nodal Operating Guide Revision Request (NOGRR) establishes frequency and voltage ride-through requirements for Large Computational Loads (LCLs).