NOGRR #261 · Revision Request
NOGRR261 Move OBD to Section 8 – Procedure for Calculating RRS Limits for Individual Resources
ReasonGeneral system and/or process improvement(s)
Created2024-01-08
Approved2024-04-11
Sections Affected
2.3.1.2.1 and 8N (new)
Summary
This Nodal Operating Guide Revision Request (NOGRR) incorporates the Other Binding Document “Procedure for Calculating Responsive Reserve (RRS) Limits for Individual Resources” into the Nodal Operating Guide.
Timeline
- Dec 21 '23
-
Jan 8 '24
ROS ROS MeetingROSRecommended for Approval Recommended for approval“to recommend approval of NOGRR261 as submitted” — Passed→ Impact Analysis Consideration
-
Feb 1 '24
ROS ROS Meeting - Webex OnlyROSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 1/8/24 ROS Report and 12/21/23 Impact Analysis for NOGRR261” — Passed→ Revision Request Consideration
-
Feb 14 '24
TAC TAC MeetingTACRecommended for Approval Recommended for approval“to recommend approval of NOGRR261 as recommended by ROS in the 2/1/24 ROS Report” — Passed→ Revision Request Consideration
-
Feb 27 '24
BOARD Board of Directors MeetingBOARDRecommended for Approval Recommended for approval“to recommend approval of NOGRR261 as recommended by TAC in the 2/14/24 TAC Report” — Passed→ Revision Request Consideration
-
Apr 11 '24
PUCTPUCTApproved Approved“to approve NOGRR261 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
-
—
Posted since the last meeting