NOGRR #246 · Revision Request
NOGRR246 Related to NPRR1161, Clarify AVR Notification Requirements for IRRs
ReasonAddresses current operational issues
Created2023-03-02
Approved2023-07-20
Sections Affected
2.2.52.7.3.4
Summary
This Nodal Operating Guide Revision Request (NOGRR) clarifies that Intermittent Renewable Resources (IRRs), who remain synchronized to the ERCOT System but are not able to provide reactive power when not providing real power, do not have to notify ERCOT other than the Real-Time telemetered status.
Timeline
- Feb 7 '23
-
Mar 2 '23
ROS ROS MeetingROSRecommended for Approval Recommended for approval“to recommend approval of NOGRR246 as submitted” — Passed→ Impact Analysis Consideration
-
Apr 6 '23
ROS ROS MeetingROSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 3/2/23 ROS Report as revised by ROS and the 2/7/23 Impact Analysis for NOGRR246” — Passed→ Revision Request Consideration
-
May 23 '23
TAC TAC Meeting - Webex OnlyTACRecommended for Approval Recommended for approval“to recommend approval of NOGRR246 as recommended by ROS in the 4/6/23 ROS Report” — Passed→ Revision Request Consideration
-
Jun 20 '23
BOARD Board of Directors MeetingBOARDRecommended for Approval Recommended for approval“to recommend approval of NOGRR246 as recommended by TAC in the 5/23/23 TAC Report” — Passed→ Revision Request Consideration
-
Jul 20 '23
PUCTPUCTApproved Approved“to approve NOGRR246 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Rules Adopted by the Independent Organization” — Passed