NOGRR #235 · Revision Request
NOGRR235 Combining Greyboxes and Other Corrections
ReasonAdministrative
Created2021-11-04
Approved2022-02-10
Sections Affected
2.9.13.3.2.1and 6.1.3.3
Summary
This Nodal Operating Guide Revision Request (NOGRR) is submitted for transparency purposes to make small corrections to blackline and greybox language associated with NOGRR210, Related to NPRR1005, Clarify Definition of Point of Interconnection (POI) and Add Definition Point of Interconnection Bus (POIB), and NOGRR227, Add Phasor Measurement Recording Equipment Location for Main Power Transformer for Intermittent Renewable Resource (IRR), and to combine greyboxes at Section 3.3.2.1.
Timeline
- Oct 20 '21
-
Nov 4 '21
ROS ROS Meeting by Webex OnlyROSRecommended for Approval Recommended for approval“to recommend approval of NOGRR234 as submitted” — Passed→ Impact Analysis Consideration
-
Dec 2 '21
ROS ROS Meeting by Webex OnlyROSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 11/4/21 ROS Report and the Impact Analysis for NOGRR235” — Passed→ Revision Request Consideration
-
Jan 31 '22
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval“to recommend approval of NOGRR235 as recommended by ROS in the 12/2/21 ROS Report” — Passed→ Revision Request Consideration
-
Feb 10 '22
PUCTPUCTApproved Approved“to approve NOGRR235 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization” — Passed
-
—